TDOT to Let Bids for New Sligo Bridge, Flashing Beacon Light, Resurfacing Projects in DeKalb County

The Tennessee Department of Transportation plans to open bids Friday, April 5 on a construction contract for the new Sligo bridge, the installation of a flashing beacon at U.S. 70 and State Route 83, and several highway resurfacing projects in DeKalb County.
The Sligo project calls for the construction of a welded steel plate girder bridge and three retaining walls on US. 70 (state route 26) over the Caney Fork River and Sligo Road. The completion date is on or before June 30, 2016.
TDOT will open bids for the installation of a flashing beacon on U.S. 70 (State Route 26) at the intersection of State Route 83 near Kilgore’s Restaurant. The completion date is on or before July 31, 2013. Many serious traffic accidents have occurred at this intersection in recent years.
Bids will be let for:
The resurfacing (either micro-surface or thin mix overlay) on State Route 96 beginning at Center Hill Dam and extending to the Putnam County line. Project length- 2.970 miles. Completion time on or before September 30, 2013
The resurfacing (either micro-surface or thin mix overlay) of State Route 141 beginning at State Route 96 and extending to the Putnam County line. Project length- 3.330 miles. Completion time on or before September 30, 2013
The resurfacing (either micro-surface or thin mix overlay) of State Route 264 beginning at State Route 96 and extending to the Smith County line including bridge deck repair. Project length- 5.480 miles. Completion time on or before September 30, 2013.
The resurfacing (micro-surfacing) of State Route 56 beginning at Church Street and extending to the Putnam County line. Project length- 11.760 miles. Completion time on or before September 30, 2013
The resurfacing (micro-surfacing) on State Route 56 beginning at the DeKalb County line and extending to the I-40 overpass. Project length- 0.540 miles. Completion time on or before September 30, 2013
The resurfacing (micro-surfacing) of State Route 141 beginning at the DeKalb County line and extending to State Route 56. Project length- 3.410 miles. Completion time on or before September 30, 2013.

Posted in News and tagged .